Office Renovation

Office Renovation — Process Notes

2025 Ankara

An office renovation run while staff stayed on site, documented stage by stage.

A 260 m² renovation carried out in a working office, with staff still on site. This page is about process rather than pictures: which decisions we took and why, where we changed the plan, and how long each stage actually ran.

  1. 01 Duration: 1 week

    Survey and findings

    The first issue the survey turned up was that the wiring above the suspended ceiling did not match the drawings. The plan showed three separate socket circuits; on site they all ran off a single one. As it stood, the desk layout planned for the open-plan area could not be built.

    We put two options to the client: rewire completely, or re-plan the desk layout around the existing circuits. They chose the rewire. We set out the cost and schedule impact of that decision in writing before any work started.

    Existing condition survey
  2. 02 Duration: 2 weeks

    Strip-out and services

    Because the office stayed open, the strip-out ran in two phases rather than one. Half the floor was closed off with a temporary partition; a dust barrier and separate ventilation protected the side still in use. Noisy work moved outside office hours.

    Power and data were fully renewed, and the ceiling was dropped 8 cm for the new lighting. When the old pipework in the wet area was opened up, an unexpected damp trace appeared; the waterproofing there was renewed even though it was not in the scope.

    Strip-out phase
  3. 03 Duration: 4 weeks

    Installation

    Carpet tile was chosen for the floor: the joints do not read, and a damaged area can be replaced tile by tile. Acoustic seals were fitted to the glass partitions of the meeting rooms, which is where the problem of speech carrying in from the open-plan area was actually solved.

    Lighting was split across three circuits instead of one general switch: workstations, meeting rooms and circulation. That makes it possible to work late without lighting the entire floor.

    Installation phase
  4. 04 Duration: 3 days

    Handover and checks

    Before handover every circuit was labelled and the client was given a services drawing. Any future work can locate a run without opening up a wall.

    Two snags were fixed under warranty in the first month: a door frame that had settled and started to catch, and a lighting driver replaced in a meeting room.

In a working office the hard part of a renovation is not the build; it is that people can sit down at their desks the next morning.

Project credits

Scope
Office renovation · turnkey
Area
260 m²
Duration
7 weeks
Condition
Office in use
Year
2025